Demolishing next to a neighbour: exposed walls and weathering

Demolishing a building that shares a wall with next door, or stands close to it, brings in the Party Wall Act. The main concerns are keeping the shared wall stable and weathertight once your side is gone.

Exposing a party wall

You are allowed to uncover a party wall that used to be enclosed, as long as it is given adequate weathering. If you demolish an extension built against the party wall, the newly exposed face needs protecting.

Laying the neighbour's property open

Where work lays open any part of a neighbour's land or building, the building owner must provide hoarding, shoring or temporary construction for as long as necessary, at their own expense.

Foundations

Grubbing out old foundations, or digging new ones for a replacement building, can trigger the excavation rules if the work is within 3 or 6 metres and deep enough.

Before demolition starts

  • Serve the right notices: party structure for the party wall, excavation for any digging.
  • Agree how the wall will be supported and weathered, and for how long.
  • Record the condition of the neighbour's property.

Rules outside the Act

Councils have separate controls over demolition, and some demolition in conservation areas needs planning permission.

Common questions

My neighbour knocked down their extension and left our shared wall exposed. What can I do?

The Act requires adequate weathering where a party wall is exposed. Ask them, or their surveyor, how it will be protected.

Where this comes from in the Act

Links go to the official text of the Party Wall etc. Act 1996 on legislation.gov.uk.

Planning work next to a neighbour?

Ivan Larkin can confirm which notices your project needs, prepare and serve them, and deal with your neighbour's surveyor. Fixed fees, agreed in writing first.

Call 07477 207993Send an enquiry