Notices you are likely to need
- Excavation notice, because the dig will go well below your neighbour's foundations
- Party structure notice, if you will underpin or cut into the party wall
- Sometimes notices to neighbours further along, under the 6-metre rule
What the award is likely to cover
- Detailed structural drawings and calculations, reviewed for the neighbour
- The sequence of underpinning, often in short sections
- Temporary propping and support
- Movement monitoring of the neighbour's property during the work
- Drainage and groundwater measures
- Working hours and vibration limits
Costs
Basement awards cost more than those for lofts or extensions because there is more to review and inspect. The neighbour's surveyor may need a structural engineer's input, and that cost usually falls on the building owner. Your neighbour can also ask for security for expenses, a sum held back in case the project is abandoned part-way.
Timetable
Allow longer. A basement award can take several weeks of review on top of the notice period. Starting the party wall process early, while the engineer is designing, saves time.
Underpinning without a basement
Underpinning to deal with subsidence, or to deepen foundations under a shared wall, is also party structure work and may involve excavation. The same principles apply on a smaller scale.
Where this comes from in the Act
- Section 2: Repair etc. of party wall: rights of owner
- Section 6: Adjacent excavation and construction
- Section 12: Security for expenses
Links go to the official text of the Party Wall etc. Act 1996 on legislation.gov.uk.