Conservatories and orangeries near the boundary

A conservatory or orangery is treated like any other extension under the Act. Whether you need notice depends on where it goes, how it meets the house and how deep its foundations are.

On the boundary

A dwarf wall or full-height wall built on the boundary line needs a line of junction notice.

Against a shared wall

If the roof or frame is fixed into, or bears on, the party wall, or a flashing is cut into it, that is party structure work.

Foundations

Even lightweight structures need foundations. Foundations dug within 3 metres of next door's building, and deeper than its own, need an excavation notice. Orangeries, being heavier, often have deeper foundations than people expect.

Typical examples

Design Notices usually needed
Lean-to conservatory on the back of a semi, 1 m from the boundary Excavation, if its foundations go below next door's
Orangery built up to the boundary Line of junction and excavation
Conservatory roof flashed into the shared wall Party structure

Gutters and overhangs

Keep gutters and roof edges on your side of the boundary. Overhanging a neighbour's land needs their agreement; the Act does not give you that right.

Common questions

My conservatory is exempt from planning permission. Does that matter?

No. Planning exemptions do not affect the Party Wall Act.

Where this comes from in the Act

Links go to the official text of the Party Wall etc. Act 1996 on legislation.gov.uk.

Planning work next to a neighbour?

Ivan Larkin can confirm which notices your project needs, prepare and serve them, and deal with your neighbour's surveyor. Fixed fees, agreed in writing first.

Call 07477 207993Send an enquiry